Building the ‘custom made countertop’
I planned on helping alot more today on the building of the countertop ‘framing’ but between work stuff and trying to stay out of the way, I got very little ‘kitchen time’. Jen was in there all day getting things done!! You Go Girl!
Some of the cabinet doors now have pulls (this was done 2 days ago…and they look great – still more to do)…there are 17 cabinets in the kitchen now…41 cabinet pulls for doors and drawers
Trim has been cut/installed for most of the windows and doors, baseboards painted.
The countertop framing is complete…the raw plumbing is in place…and the cement board is cut and ready to be screwed into place. We are using a bolt cutter to nip 1/4″ of the end of cement screws, since the shortest cement screw sold is a little too long. Chances of these screws ever making contact with skin is slim to none, but why take the chance…that cut would be ugly! screwing cement board into place is one of my many weekend projects….